The pavement at the Tamworth Street and Darling Street Dubbo roundabout has reached the end of its service life, showing significant signs of wear, such as shoving, heaving, and general pavement failure. Additionally, the water mains beneath the roundabout, which are approximately 100 years old, are nearing the end of their functional lifespan.

In response to these issues, Dubbo Regional Council will be conducting critical roadworks at this intersection. The upgrades aim to restore and improve road infrastructure, benefiting the entire community.


The project will be completed in two stages, starting on 8 October 2024.

  • Stage 1: Expected to last six weeks.
  • Stage 2: Will begin following Stage 1. A Courtesy Notice was sent to impacted and neighbouring residents on 7 November 2024. Works are expected to last 5 weeks.

Stage 2

Stage 2 | Roundabout Reconstruction Works

Stage 2 involves the complete reconstruction of the roundabout, including:

  • Pavement replacement
  • Central island reconstruction
  • Upgrades to the roundabout approaches
  • Reconstruction of traffic islands
  • Installation of new line markings
  • Installation of updated traffic signs

Proposed Start Date: 18 November 2024, weather permitting

Stage 1

Stage 1 | Stormwater Rectification Works

Stage 1 of the project focuses on rectifying stormwater drainage issues at the roundabout. The work includes:

  • Removal of the existing stormwater network
  • Installation of new stormwater infrastructure, including pits, lintels, and pipes, to improve drainage at the site

Duration: 6 weeks, commencing 8 October 2024

The work will involve road closures and detours in three segments, with approximate durations as follows:

  • Segment 1: Approximately 3 weeks
  • Segment 2: Approximately 1 week
  • Segment 3: Approximately 2 weeks

A pedestrian management plan is in place to manage footpath access. Pedestrians can detour around the roundabout using the ramps to support mobility accessibility.

Please refer to the map below for the exact locations of these closures. Simply click the icon’s of each segment to find out more about the traffic restrictions and detours.

❓FAQS

☝️Ask us a question

Provide a short summary of your question.

You have 150 characters left

Provide detailed information relating to your question.

You have 500 characters left

Select a respondent from the list that you would most like to answer your question.

Moderation Policy

These are the people that are listening and responding to your questions.

Project Engineer

Dubbo Regional Council

Engagement & Customer Insights Team

Dubbo Regional Council

{{ question.username }} asked

{{question.description}}

{{ answer.respondent.name }}
| Edited

Answer this question

Select the respondent who will be marked as answering the question

Provide the answer to the question. Answer can be saved as draft and published when complete.

No questions found

Related projects




Contact Us

Phone (02) 6801 4000
Website www.dubbo.nsw.gov.au
In writing

P.O. Box 81
Dubbo NSW 2830

Social Media